- Site cleaning
- Temporary Shed Construction
- Foundation Digging
- Soil digging for Pillars
- Soil digging for foundation
- Start carpenter work
- Footing and Pillar Base
- Pillars until Plinths
- Stone Foundation
- Plinth beam
- Fill soil inside Plinth area.
- Setting up main door frame and other room door frames
- Wall construction until window frame base
- Setup all window frames
- Setup lintel and saja
- Wall construction until beams
- Setup kitchen ventilators for exhaust fans OR bathroom ventilators
- Bar bending work for beams and roof
- Inverter beams
- Storing Water on top of roof
- Electric pipes
- Clear any blockage in the roof pipes
- Laying electric pipes in the walls and setup electric boxes
- Plumbing work for kitchen and bathroom
- Setup water pipes and sewage pipes
- Setup Indian latrine
- Water proofing for bathrooms
- Close all water and sewage pipes with temporary caps
- Setup kitchen platform and sink
- Tiles laying in bathroom and kitchen for walls
- Plastering of roof and walls inside
- Plastering of outside walls
- Applying putty for window frames
- Fixing window frames
- Granite and Marble Lying
- Granite tiles Laying in bathroom
- Fixing Bathroom Fittings
- Finishing outside plumbing work and tank
- House Elevation
- Painting
- Interior Painting
- Exterior Painting
- Decorated Painting
- Wallpaper Fixing
- Electric work
- Electrical wiring
- Dummy plate fixing/ electrical holders
- Electrical switches and Socket setup
- Laying electric service wire from pole to meter board
- Fixing meters in panel board.
- Digging pit for power earth
- Digging pit
- Motor & connection to tank
- Sewage lines to pit
- Parking tiles
- Compound wall